Erimus Year 6 Investment Programme April 2010-March 2011

Erimus Housing has to date invested nearly £130m delivering a major programme of modernisation work to bring our homes up to modern day living standards. However the modernisation work to homes is an ongoing process and the improvement work to homes will continue throughout the coming year and beyond.

The extent of the work carried out to homes will depend upon the findings of a survey carried out by an Erimus Housing inspector, who will assess the age and condition of every home's fixtures and fittings. Where needed, new fittings will be installed as part of the modernisation work and internal and external property repairs may be carried out at the same time. Listed below are the estates inculded in this year's programme.

Our 2010/2011 Modernisation Programme

Estate No of Properties Work may Include Estimated Start and Finish Dates
Berwick Hills
593
Replacement bathrooms, internal doors and external work
April 2010 - March 2011
Landgridge flats
60
Replacement heating, new bathrooms, internal doors and external work
July 2010- August 2010
Park End
272
Replacement bathrooms, internal doors and external work
August 2010 - December 2010
Grove Hill (Birchwood Ave (9 properties), Marton Burn Road (12 properties), Keith Rd (one property)
22
Replacement windows & doors, replacement heating, electrical work, new kitchen, new bathroom, internal doors and external work
April 2010 - May 2010
Hemlington (Dales Park)
210
Replacement heating and internal doors
May 2010 - August 2010

 

You can use the address finder facility in this section to check whether your property is in the 2010/2011 investment programme by clicking here and typing the first line of your address into the address finder search box.

Our 2010/2011 Estate Improvement Programme

To date we have spent £6.5m on estate improvement work. All estate improvement work is subject to a survey but can include fencing repairs and recoating or where appropriate, new fencing, repairs to pathways, boundary walls and kerb lines. Listed below are the estates programmed for work between April 2010 and March 2011.

Estate No of Properties Work may Include Estimated Start and Finish Dates
Grove Hill
350
Repair or renewal of fencing depending on condition and recoating of retained fence lines, repairs to pathways, restoration of boundary walls.
April 2010 - September 2010
Acklam
10

Repair or renewal of fencing depending on condition and recoating of retained fence lines, repairs to pathways, restoration of boundary walls.

May 2010 - July 2010
Hemlington
760
Repair or renewal of fencing depending on condition and recoating of retained fence lines, repairs to pathways.
May 2010 - Nov 2010
Pallister Park
770
Repair or renewal of fencing depending on condition and recoating of retained fence lines, repairs to pathways, restoration of boundary walls.
Sept 2010 - March 2011
Stainton
12
Repair or renewal of fencing depending on condition and recoating of retained fence lines.
July 2010
Tollesby
19
Repair or renewal of fencing depending on condition and recoating of retained fence lines.
July 2010 - August 2010
Town Farm
63

Repair or renewal of fencing depending on condition and recoating of retained fence lines.

Sept 2010 - Nov 2010